At our recent rough-in walk-through we were able to take some decent photos of the inside of the house. Here they are:

Temporary front door
Roof trusses wtih roof tiles laid
Evaporative cooling and ducted heating vents
Roof over rear of house
 Frame for Ensuite spa bath

 Insulation bats ready to be installed

Theatre Room with sound insulation installed 

Fireplace provision 

Gyprock delivered 

Cornices delivered 

Looking from rear of house to front door 

Master Bedroom insulated 

Frame for tub in Bathroom

 Ducted Vacuum piping
There's lots more, but it's hard to know where to draw the line. These pics should give a good idea of what stage we're at.